Client: Cambridge University Project: AC UPS & Generator Supply: Complete Turnkey Package

Cambridge University nominated Harland Simon UPS as their main contractor to upgrade the Power Protection System to support their main computer system which supports the Cambridge wide educational network.

Harland Simon’s role as main contractor included responsibility for all site activities including:-

  • Health & Safety
  • Site access, control and monitoring
  • Procurement of all main contractors including: Building Services, Mechanical Installation, Electrical Installation, Air Conditioning & Generator

The project was completed within budget and the 24 week project timescale.

The equipment provided was supplied strictly in accordance with the Cambridge University Estate Management Departments detailed technical specification.

“In addition to supplying the generator and UPS systems Harland Simon was appointed as the main contractor, responsible for all site work and bringing the project in on time”, Andy Parfitt, Sales Director HSUPS.

Project Summary:

  • 300kVA Diesel Generator with 12 hour Base Tank
  • 2 x N+1 Redundant 100kVA/20 minute PW9340 UPS
  • Electrical Installation
  • Building Services
  • Project Management
  • On-Going Service and Maintenance of the Entire Installation